حساب البرنامج الزمني لمشروع هندسي باستخدام برنامج البرايموفيرا
Loading...
Date
Journal Title
Journal ISSN
Volume Title
Publisher
جامعة الشيخ عبدالله البدري
Abstract
The research aims to define the time program and it’s important for any
engineering projects, as well as to study project management process in general,
and the time management process for engineering projects in particular using the
primavera program ,as well as identify several methods such as the Gantt chart
and the critical path .
Area of 280 square meters, and applying the primavera program was
applied a residential building with the program, if was found that the
total time to implement the projects was 370 days.
According to the schedule of materials, quantities, workmanship, and
labor available for project.